support@w4writers.com +44 7743 307695
Mar 01, 2024

Assignment Task

Hydropower Project

The government of a developing country in South-East Asia is considering the construction of a 300MW hydro-electric power generating scheme. This will entail the construction of a dam and the flooding of an area of 2000 hectares of tropical rain forest. The power generated is intended to feed into the grid at times of peak power usage (i.e. the plant will not be generating 24 hours a day and 365 days a year).

You are required to undertake a benefit-cost analysis of the project which considers the impacts detailed below. The analysis is to be done over a period of 60 years using a discount rate of 6%. All values are in 2023 US$.

Question 

1. The dam is mainly constructed of concrete and steel. Over the first 7 years of construction 1.75 million tonnes of concrete will be used (0.25 million tonnes per year). This amount represents a significant proportion of this country’s concrete manufacturing capacity and so will have an effect on the market price. Prior to the project the average sale price of concrete is $120 per tonne at an equilibrium quantity of 1 million tonnes. If the project goes ahead it is expected to shift the demand curve for concrete and increase the market equilibrium price to $130 (at an equilibrium quantity of 1.2 million tonnes). At this higher price some existing consumers of concrete will be displaced.

Calculate the annual costs of concrete using both a diagram and the Harberger equation. Assume that all supply and demand curves are straight lines and any shifts are parallel.

2. Conduct a benefit-cost analysis of the project using your answer to 1 above as a measure of the costs of the concrete that the project requires and which also includes the following costs and benefits (all in millions of US$). The dam will take 8 years to construct, all benefits will begin from Year 9.

Construction costs

  Year 1 2 3 4 5 6 7 8
Steel   10 10 10 10 10 10 10  
Labour   15 15 15 15 15 15 15 7.5
Generating equipment         10 10 25 25 30
Other costs   2.5 3 3.7 4 2.5 2.5 2.5 2.5

 

Operating costs

These are $13.5 million per year, they start in Year 9 and are assumed to remain constant through the life of the project.

3. A further benefit provided by the construction of the dam is a reduction in flood risk. The low-lying, productive and densely populated farmland downstream of the proposed dam is subject to occasional (a frequency of once every twenty-five years) severe flooding which has been calculated to cause $1.5 billion of damage to property, crops and livestock, and in terms of loss of life.

Incorporate this impact into the analysis assuming that the construction of the dam will reduce the probability of a flood occurring from once every 25 years to once every 100 years (with the same projected damage cost). How does this change the recommendation made in your answer to Question 2, again explaining the reasoning for your revised recommendation?

4. At what discount rate does the project (including flooding reduction benefits) become unviable?

5. To which level do benefits from electricity production need to fall before the project (including flooding reduction benefits) becomes unviable?

Recent Post

Order this Assignment now

Total: GBP120

fables template